Answer:
0.1241
Step-by-step explanation:
Given that:
Critical path = 37 days
Variance total = 27 days
Completion date (x) = 43 days
We obtain the Zscore :
Zscore = (x - critical path) / variance total
Zscore = (43 - 37) / √27
Zscore = 6 / √27
Zscore = 1.1547
Zscore = 1.155
Hence, probability of completing in 43 days :
P(Z > 43) = 1 - P(Z < 43)
P(Z < 43) = 0.8759
P(Z > 43) = 1 - 0.8759 = 0.1241
Music students and art students at a middle school were surveyed to choose a cardiovascular activity: playing sports or dancing.
Do you prefer dancing or playing sports?
Playing sports Dancing Row totals
Music students 32 15 47
Art students 31 22 53
Column totals 63 37 100
What is the marginal frequency of students who chose dancing?
15
22
37
53
The marginal frequency of students who chose dancing is 37.
The correct answer to the given question is option 3.
The marginal frequency of students who chose dancing can be calculated by adding up the number of students who chose dancing in each row or column. In this case, we need to add up the number of art students who chose dancing (22) and the number of music students who chose dancing (15), which gives us a total of 37. This is the marginal frequency of students who chose dancing.
Based on the survey results, it appears that a slightly higher percentage of art students prefer dancing (41.5%) compared to music students (31.9%). However, both groups of students seem to be fairly evenly split between dancing and playing sports, with a slight preference for playing sports overall.
It's worth noting that cardiovascular activity is important for overall health and well-being, and both dancing and playing sports can provide great opportunities for exercise and physical activity. Additionally, both activities can also be enjoyable and provide a sense of community and social connection, which is important for middle school students who are still developing their social skills and relationships. Ultimately, the choice between dancing and playing sports will depend on individual interests, preferences, and abilities.
For more such questions on frequency, click on:
https://brainly.com/question/254161
#SPJ8
what is the solution for 96 = 12d?
d = 8
Divide both sides of the equation by the same term
Answer:
d = 8
Step-by-step explanation:
Step 1: Divide both sides by 12.
\(12d/12 = 96/12\) \(d=8\)Therefore, the solution is 8.
Questions
1. There are 30 students in a class: 16 boys and 14 girls. What is the probability that a boy will be chosen at random?
2. A bag contains 3 green marbles, 6 blue marbles and 6 red marbles. One marble is taken out of the bag at random.
What is the probability of choosing:
(1) a red marble?
a
(11)
a green marble?
3.
(a) What is the probability of choosing the letter B at random from the word ALPHABET?
+
Answer:
1. 8/15
2. Green marble: 3/15
Red Marble: 6/15
Blue marbles: 6/15
3. a 1/8
Answer:
1: 8/15
2: a: 2/5
b: 1/5
3: 1/8
Step-by-step explanation:
1:
16/30 chance
simplify
8/15
2:
3 + 6 + 6 = 15
red: 6/15 --> 2/5
green: 3/15 --> 1/5
3:
1/8
NEED HELP!! I"LL GIVE YOU BRAINLIEST!! Find the value of b. a = 3 and c =12
Answer: b = 11.62
Step-by-step explanation:
We can use this formula to solve for b:
\(b^{2} =\) \(\sqrt{c^{2}-a^{2} }\)
\(b^{2} =\) \(\sqrt{12^{2}-3^2 }\)
\(b^2= \sqrt{144-9}\)
= 11.61895004
We can round that to 11.62.
Hope this helped!
If 3220 = 8+7, what is the value of c?
01
02
03
05
Answer:
c = 3
Step-by-step explanation:
\( 32^{2c} = 8^{c + 7} \)
\( (2^5)^{2c} = (2^3)^{c + 7} \)
\( 2^{10c} = 2^{3c + 21} \)
\( 10c = 3c + 21 \)
\( 7c = 21 \)
\( c = 3 \)
Joe says 4.02 times 0.3 is about 12. Does this make sense? Explain your thinking.
Answer:
No, it doesn't.
Because 0.3 is smaller than 1, so the product should be less than 4.02.
Let me know if this helps!
Which is misleading about the data shown on the figure?
Number of members
Look at the photo
The misleading about the data shown on the figure is the clas width
Which is misleading about the data shown on the figure?From the question, we have the following parameters that can be used in our computation:
The histogram
On the histogram, we have the following readings
1 - 2021 - 3031 - 4546 - 65From the above, we can see that
The above readings are not consistent i.e. the class widths are not equal
Hence, the misleading about the data shown on the figure is the clas width
Read more about graphs at
https://brainly.com/question/28350999
#SPJ1
3/16 divided by 2 1/4
Factor. Please show work
Answer:
Step-by-step explanation:
f(x)=2(2x+3)(x−3)
hope this helps
please answer or i move down grade again
Answer:
x is a 33° angle
Step-by-step explanation:
The two angles are supplementary meaning the measure of both angles adds up to 180°. You can tell they are supplementary because the angle is a straight line. so all you need to do is subtact 147 from. 180 to get the measure of x .
Answer:
x+147=180 ( sum of supplementary angle)
or, x = 180-147
or, x = 33
so the value of x is 33°
I NEED HELP PLSSSSSSSS
Answer:
X >>>>> Y
–1 >>>> 16
0 >>>>> 8
1 >>>>> 4
2 >>>>> 2
3 >>>>> 1
Step-by-step explanation:
From the question given above,
y = 8 × (½)ˣ
When x = –1, y =?
y = 8 × (½)ˣ
y = 8 × (½)¯¹
y = 8 × 2
y = 16
When x = 1, y =?
y = 8 × (½)ˣ
y = 8 × (½)¹
y = 8 × ½
y = 4
When x = 2, y =?
y = 8 × (½)ˣ
y = 8 × (½)²
y = 8 × ¼
y = 2
When x = 3, y =?
y = 8 × (½)ˣ
y = 8 × (½)³
y = 8 × ⅛
y = 1
SUMMARY:
X >>>>> Y
–1 >>>> 16
0 >>>>> 8
1 >>>>> 4
2 >>>>> 2
3 >>>>> 1
34 miles
30 mph
How much time will it
take for these two
vehicles to meet?
55 mph
[?] hours
Answer:
0.4 hours
Step-by-step explanation:
or 24 minutes :D
1) There are 56 people at a party. Each table has 8 seats. How many tables are
needed so all of the people have a seat?
56 +
= 8
6
54
Answer:
56 / 8
Step-by-step explanation:
What number decreased by 40 is 5 times that number?
Answer:
-10
Step-by-step explanation:
Let the number be x
x - 40 = 5x
⇒ -40 = 5x - x
⇒ 4x = -40
⇒ x = -40/4
⇒ x = -10
Answer:
-10
Step-by-step explanation:
Let the number be x
x - 40 = 5x
4x = -40
x = -10
How to solve this 75,465(7)
Based on context clues or what's been given,
Parenthesis indicate multiplication.
75,465 * 7
Now calculate:
528,255
Answer: 528,255
Step-by-step explanation:
u just multiply 75,465 by 7 and you get 528,255
if there is a number next to another number that is inside the parentheses then that means you multiply the numbers together
for example: 12(3) means multiply 12 by 3 and u get 36
Between which two consecutive integers is \(\sqrt{201}\)
Answer:
14 and 15
Step-by-step explanation:
\(196<201<225 \\ \\ \sqrt{196}<\sqrt{201}<\sqrt{225} \\ \\ 14<\sqrt{201}<15\)
A number is between 40 and 45 . It has prime factors of 2 and 11. What is the number?
Answer: 42
Step by step:
42 is divisible by both 7 and 2
Answer:
44
Step-by-step explanation:
4 x 11 = 44
2 x 22 = 44
For each of the following, identify the exam score that should lead to the better grade. In each case, explain your answer.
a) A score of X = 74 on an exam with μ=82 and σ=8; or a score of X = 40 on an exam with μ=50 and σ=20.
b) A score of X = 51 on an exam with μ=45 and σ=2; or a score of X = 90 on an exam with μ=70 and σ=20.
c) A score of X = 62 on an exam with μ=50 and σ=8; or a score of X = 23 on an exam with μ=20 and σ=2.
The exam scores , that will lead to the better grade is
(a) the score of "X=40" in exam with μ = 50 , σ = 20 ;
(b) the score of "X=51" in exam with μ = 45 , σ = 2 ;
(c) Both the score will lead to better grades .
Part(a) : In order to find which score leads to better grade, we calculate the z-scores for both scores and compare :
The score of X = 74 on the first exam is :
⇒ z = (74 - 82)/8 = -1 ;
The score of X = 40 on the second exam is :
⇒ z = (40 - 50)/20 = -0.5 .
The z-score of -0.5 is > -1,
So , the score of X = 40 on the second exam lead to better grade because the score of 40 is closer to mean of second exam (50) and has a smaller deviation from mean (20) than score of 74 on first exam .
Part(b) :
The score of X = 51 on the first exam is :
⇒ z = (51 - 45)/2 = 3 ;
The score of X = 90 on the second exam is :
⇒ z = (90 - 70) / 20 = 1 .
The z-score of 3 is > 1 ,
So , the score of X = 51 on the first exam should lead to the better grade.
Part(c) :
The score of X = 62 on the first exam is :
⇒ z = (62 - 50) / 8 = 1.5 ;
The score of X = 23 on the second exam is :
⇒ z = (23 - 20) / 2 = 1.5 .
Both scores have the same z-score of 1.5, they should lead to the same grade.
Learn more about Z-Score here
https://brainly.com/question/15016913
#SPJ4
A state lotto has a prize that pays $900 each week for 20 years.
Find the total value of the prize: $
If the state can earn 5% interest on investments, how much money will they need to put into an account
now to cover the weekly prize payments?
Reminder: There are 52 weeks in a year.
The total value of the prize is $936,000.
The state will need to invest $591,498.96 now at a 5% interest rate to cover the weekly prize payments for 20 years.
What is the total value of the prize?The total value of the prize is calculated by multiplying the annual payment by the number of years and is equal to:
= $900/week x 52 weeks/year x 20 years
= $936,000.
How much money is needed to put into the account?We need to use the present value formula which is: PV = PMT x [1 - (1 + r)^-n] / r
Plugging in the values:
PV = $900 x [1 - (1 + 0.00096154)^-1,040] / 0.00096154
PV = $900 x 657.221075423
PV = $591,498.968.
Read more about state lotto
brainly.com/question/28988219
#SPJ1
Find the Prime Factorization of -165
Answer:
(-1)(11)(3)(5)
Step-by-step explanation:
First off: -165 separates into the factors (-1) and (165). Next, we divide 165 by 15, obtaining 15(11).
So far, we have (-1)(11)(15).
15 is still factorable. We get:
(-1)(11)(3)(5), which is the desired prime factorization of -165.
Solve 4(x - 3) - 2(x - 1) > 0.
OXIX > 2)
OxIx>7)
Oxlx> 14)
O x 1 x>5)
Answer:
4(x - 3) - 2(x - 1) > 0
(4x - 12) - 2x + 2) > 0
4x - 2x - 12 + 2 > 0
2x - 10 > 0
2x > 10
x > 10/2
x > 5
I neead a fast answer 50pts fast (+Brainliest for right answer)!!!!
Answer: The description of that transformation is the triangle is rotated 90 degrees clockwise. Then, it's moved to the right TWICE. Finally, you go down 2 times.
Step-by-step explanation:
Hope this helps :)
triangle B is in dofferent orientation from triangle B so we know it was either mirrored or rotated. Triangle B isnt in the exact opposite orientation as A so we know it wasnt mirrored. So we now know that it was rotated and know we have to find the point of rotation. we can tell that the rotation was 270 degrees anti clockwise since it cant be clockwise because no points of rotation match. since we know triangle A was rotated 270 degrees anti clockwise to get triangle B we cant find the point of rotation by seeing which point works and if we test the points we will see that (0;-1) is the point of rotation. So triangle A was rotated 270 degrees anti clockwise on the point (0;-1) to make triangle B
PLS HELP ASAPPP
I really need help
question: write in standard form.
2x^2+x^3-3+4x^5
Answer:
4x^5 + x^3 + 2x^2 -3
Step-by-step explanation:
Standard form is ( put simply ) the order the numbers are from highest to lowest. So the standard form of the equation would be 4x^5 + x^3 + 2x^2 -3
When graphed in the (x,y) coordinate plane, at what point do the lines x - y = 12
and y= 2 intersect?
Answer:
(14, 2).
Step-by-step explanation:
x - y = 12
y = 2
Solving this system:
Plug y = 2 into the first equation:
x - 2 = 12
x = 14.
Therefore the point of intersection is at (14, 2).
Kevin's bank deducts a service fee from his account every month.
In one year, the bank deducts a total of $90 in fees. Twice each
month, Kevin's paycheck is directly deposited into his account.
The amount of each paycheck is $1,150. Which expression
represents the monthly change in Kevin's bank account?
The expression that represents the monthly change in Kevin's bank account is $2,300 - $7.50 = $2,292.50
How to find the expressionIn one year, which has 12 months, the bank deducts a total of $90 in fees. To find the monthly change in Kevin's bank account, we need to divide this total by 12:
Monthly service fee = $90 / 12 = $7.50
Kevin's paycheck is deposited twice each month, so his total monthly income from his paychecks is:
Monthly income = 2 * $1,150 = $2,300
Therefore, Kevin's monthly change in his bank account is:
Monthly change = Monthly income - Monthly service fee
Monthly change = $2,300 - $7.50 = $2,292.50
So the expression that represents the monthly change in Kevin's bank account is $2,300 - $7.50 = $2,292.50
Learn more about expression at:https://brainly.com/question/1859113
#SPJ1
god gave me 3 apples but the devil would have gave me 23 have many apples do i have?
A man wants to mesure the height of a nearby building. He places a 7ft pole in the shadow of the building so that the shadow of the pole is exactly covered by the shadow of the building. The total length of the building’s shadow is 162ft, the pole casts a shadow that is 5.5ft long. How tall is the building? Round your answer to the nearest foot.
The height of the building is approximately 227 feet.
In the given question, a man wants to measure the height of a nearby building. He places a 7 ft pole in the shadow of the building so that the shadow of the pole is exactly covered by the shadow of the building.
The total length of the building's shadow is 162 ft, and the pole casts a shadow that is 5.5 ft long. We have to determine the height of the building.The given situation can be explained with the help of a diagram.
As shown in the figure above, let AB be the building and CD be the 7 ft pole. The height of the building is represented by the line segment AE, which is to be determined. Let the length of the shadow of the pole be CD and that of the building be BD.
Therefore, the length of the total shadow will be BC or CD + BD.According to the question, the shadow of the pole is exactly covered by the shadow of the building. This implies that the two triangles AEF and CDF are similar. Hence, the corresponding sides are proportional. Therefore, we have:AE/EF = CD/DF
On substituting the values from the given data, we get:
AE/(EF + 5.5) = 7/5.5.... (1)
Similarly, we can write from the given data:
BD/DF = 162/5.5.... (2)
From equations (1) and (2), we can write:
AE/(EF + 5.5) = BD/DF => AE/(EF + 5.5) = 162/5.5.... (3)
On solving the above equation for AE, we get:
AE = (7/5.5) × (162/5.5 - 5.5)≈ 226.6 ft
Therefore, the height of the building is approximately 227 feet.
For more such questions on height, click on:
https://brainly.com/question/28122539
#SPJ8
What is f(4) for the function f(x)= 6x+7?
Answer:
31
Step-by-step explanation:
f(4) = 6x4 + 7
= 24 + 7
= 31
Pablo used a total of 5 3/4 gallons of gas while driving his car. Each hour he was driving, he used 5/6 gallons of gas. What was the total number of hours he was driving? Write your ans
Definitions for vocab
Answer:
when whered then they
Step-by-step explanation: